Overhead crane span and lifting height are the two layout parameters that determine everything else in your factory crane design. Пролет is the horizontal distance between the centerlines of the runway rails; lifting height (also called hook travel) is the vertical distance the hook can rise from its lowest to its highest position. Get either wrong at the design stage and you will either waste structural budget on over-specified steel or — more expensively — discover on installation day that your loads cannot clear the machinery below the hook.
Factory planners and equipment managers face the same two concrete questions: What span do I specify, given my building column spacing? And what lifting height do I need, given my building’s usable headroom? Both calculations look simple on the surface, but each hides a stack of deductions — end-beam protrusions, hoist body height, hook deadweight travel distance, top safety clearance — that add up to 700–1,000 mm or more of “lost” headroom that generic articles rarely quantify.
This guide works through both calculations step by step, with real numbers, then shows how the arithmetic changes for single-girder vs. double-girder configurations, and what to do when headroom is genuinely tight.
Получить цитатуUnderstanding Overhead Crane Span and Lifting Height


What Span Means — and What It Is Not
Overhead crane span is the center-to-center distance between the two runway rails, not the width of your building and not the length of the bridge girder. It is the dimension that directly controls how much of your floor plan the crane can serve, and it is the first dimension a supplier needs before anything else can be quoted.
The relationship to building width is straightforward in principle: span equals building column-center spacing minus twice the distance from column center to rail center. In practice that rail-center offset depends on your runway beam geometry and bracket design, but a commonly used rule of thumb for preliminary planning is:
Crane span ≈ Building column-center spacing − 1.0 m to 1.5 m
So a workshop with columns spaced 18 m apart will typically accept a 16.5 m or 17 m span crane, not an 18 m one. The gap is not wasted space — it is the room needed for runway beams, end-stop buffers, and the 100 mm minimum safety clearance each side between end beams and the building structure, as referenced in FEM 1.001 crane design rules and GB/T 3811.
What this means for planning: if your production process requires the hook to reach within 500 mm of each side wall, your column spacing needs to be designed around the crane, not the other way around. In greenfield factories, crane span should drive structural column spacing — not be adjusted to fit an already-fixed grid.
What Lifting Height Means — and the Hidden Components Inside It


Lifting height is not simply “how high off the floor do I need to lift my load.” It is the net hook travel the crane can deliver, and it is determined by subtracting a stack of fixed mechanical and safety dimensions from your building’s usable headroom.
The full formula for required building headroom (measured from finished floor to the underside of the lowest roof structure or obstructing beam) is:
Required headroom = Lifting height needed + Hoist body height + Hook approach (deadweight travel) + Top safety clearance
Each component, explained:
- Lifting height needed (H): The actual working requirement — how high your load must rise above floor level, including any fixtures or spreader bars attached to the hook.
- Hoist body height (h₁): The vertical dimension of the hoist unit itself (wire rope hoist or chain hoist), measured from the hook in the uppermost position to the top of the hoist drum or chain pocket. This ranges typically from 560 mm to over 1,000 mm depending on hoist capacity and type; low-headroom European-style hoists are specifically engineered to compress this dimension.
- Hook approach / deadweight travel (h₂): The minimum distance the hook block must hang below the hoist drum even when fully retracted, due to the geometry of the hook block assembly. Typically 600–800 mm for wire rope hoists in the 5–32 ton range; confirm with the specific hoist model data.
- Top safety clearance (h₃): The minimum gap required between the top of the crane bridge and the lowest roof member or obstruction. FEM guidelines and GB/T 3811 both reference a minimum of 200 mm; in practice 300–400 mm is often used to allow for roof deflection and installation tolerances.
Worked example — single-girder crane, 10-ton, 12 m span:
Suppose a factory has 8.0 m from finished floor to the underside of roof purlins, and the process requires lifting loads to 5.5 m above floor.
| Компонент | Dimension |
|---|---|
| Required lifting height (H) | 5 500 мм |
| Hoist body height (h₁, reference value) | ~763 mm |
| Hook approach (h₂, reference value) | ~683 mm |
| Top safety clearance (h₃) | 200 мм |
| Total headroom required | 7,146 mm |
Available headroom is 8,000 mm → 8,000 − 7,146 = 854 mm margin. The 5.5 m lifting height is achievable with this building. If the process had required 6.0 m of lifting height, total required headroom would reach 7,646 mm — still within the 8,000 mm building, but with only 354 mm margin. Margins below 300 mm should trigger a low-headroom hoist review.
These reference figures for h₁ and h₂ are illustrative of the calculation method; actual values must be confirmed against the specific hoist model’s technical drawing before finalizing building height or crane order.
Span Calculation: Step-by-Step for New and Existing Buildings
Step 1: Establish Your Column-Center Spacing or Available Rail Width
For new buildings, this step is where the crane consultant and the structural engineer must align before any columns are poured. The right sequence is: define required crane span first → structural engineer designs column grid to match → building width follows. Reversing the sequence — fixing column grid then asking what crane fits — is the single most common planning error in factory design, and it routinely produces either unnecessarily narrow spans or requires expensive structural modifications.
For existing buildings, measure the clear distance between column flanges on both sides of the bay, then subtract the runway beam width and bracket protrusion on each side to find the available rail centerline-to-centerline distance. This is your maximum possible span. For detailed guidance on classification standards that govern crane structural design, refer to ISO 4301 crane classification.
Step 2: Apply the End-Beam Deduction
On a top-running overhead crane, the end beam extends past the rail centerline on each side. For single-girder cranes, half the end-beam box section width is typically around 130–150 mm; add the 100 mm minimum safety gap, and each side accounts for roughly 230–250 mm of deduction. Both sides together therefore reduce available span by approximately 460–500 mm from the rail-to-rail opening.
This is why a 12.47 m clear column-to-column distance typically yields a 12 m span crane, not a 12.5 m one.
Step 3: Confirm Runway Beam Level and Rail Height
The runway rail sits on top of the runway beam, which itself adds height to the underside-of-structure measurement. Rail height (commonly 40–95 mm depending on rail type, e.g., QU70 to QU100) plus beam depth must be subtracted from your usable headroom before calculating available lifting height. This is frequently overlooked in early layout sketches and accounts for 150–400 mm of additional headroom loss.
Step 4: Cross-Check Against the Hoist Dimension Stack
Once tentative span and rail height are set, run the headroom formula from the section above with the actual hoist model dimensions. If the numbers don’t close, the options — in order of cost — are: (a) select a low-headroom hoist, (b) lower the runway beam/rail level if structure permits, (c) raise the roof or add a raised bay in a new building.
Lifting Height Calculation: Headroom-Limited vs. Process-Driven Scenarios
Process-Driven: You Know What Lifting Height You Need
This is the simpler case. Define the required lifting height from process requirements (tallest load + clearance over the tallest obstruction it must pass), run the headroom formula, and confirm that your building height supports the result. If not, you have a structure problem, not a crane problem.
A useful cross-check: take your process-required lifting height, add 2,000 mm as a rough allowance for hoist body + hook approach + clearance (conservative for most wire rope hoist configurations), and compare to your building’s usable headroom. If building height is less than (required lifting height + 2,000 mm), a detailed check with actual hoist dimensions is mandatory before ordering.
Headroom-Limited: Your Building Sets the Ceiling
This is the harder and more common case in existing factories. Here the calculation runs in reverse: start with available headroom, subtract the fixed mechanical and safety components, and the remainder is your achievable lifting height.
Achievable lifting height = Available headroom − h₁ − h₂ − h₃
Using the same reference values from the worked example: a building with 7.0 m usable headroom delivers approximately 7,000 − 763 − 683 − 200 = 5,354 mm of achievable lifting height with a standard wire rope hoist. If your process needs 6.0 m, you are short by ~650 mm — and no amount of ordering a “bigger crane” will fix it. The fix is a low-headroom hoist (which compresses h₁), or accepting a lower working height.
Low-Headroom Configurations: When the Numbers Are Tight
When overhead crane span and lifting height requirements conflict with constrained building headroom, three design paths exist within overhead crane configurations:
Low-headroom wire rope hoist: Redesigned drum and rope-guide geometry that reduces hoist body height by typically 200–400 mm versus a standard hoist of the same capacity. Voitto’s Low Headroom Crane uses this approach, covering 1–20 ton capacity with spans up to 31.5 m — the same span envelope as a standard single-girder crane, but with materially more hook travel in a given building.
Underslung (underhung) crane: The bridge travels on the lower flange of the runway beam rather than on top of it, eliminating rail height entirely and recovering the full beam depth as usable headroom. The tradeoff is reduced span range (Voitto’s Подвесной кран covers 3–16 m) and lower capacity ceiling (up to 10 ton in typical configurations), because the load is now hung below a beam in bending rather than above a rail in direct compression.
European HD advanced design: A compact hoist and end-truck geometry that reduces both hoist body height and the distance between girder top and roof structure. Voitto’s Европейский HD усовершенствованный подвесной кран offers spans from 7.5 to 25.5 m and lifting heights from 6 to 12 m in a package optimized for buildings where standard cranes simply cannot fit without structural work.
The choice among these three is driven primarily by two numbers: your minimum available headroom and your required span. If both are tight simultaneously, the underslung design wins on headroom recovery but loses on span. If span is critical and headroom is only marginally short, a low-headroom hoist on a standard top-running bridge is typically the right path.
Overhead Crane Span and Lifting Height by Crane Type: A Decision Reference
The table below summarizes overhead crane span and lifting height ranges for Voitto’s overhead crane and EOT crane range, to support preliminary layout planning. All figures are reference ranges; specific configurations must be confirmed against the current product specification sheet.
| Тип крана | Диапазон производительности | Typical Span Range | Typical Lifting Height Range | Best Fit Scenario |
|---|---|---|---|---|
| Однобалочный подвесной кран | 1-32 t | 7.5-31.5 m | 6–30 m | General manufacturing, moderate duty |
| Двухбалочный подвесной кран | 5-800 t | 10-50 m | 10–40 m | Heavy loads, long spans, process cranes |
| Европейский HD усовершенствованный подвесной кран | 1–12.5 t | 7.5–25.5 m | 6–12 m | Low-headroom buildings, space-efficient layout |
| Кран EOT | 1–800 t | 7.5-31.5 m | 6–30 m | Standard industrial/workshop applications |
| Low Headroom Crane | 1–20 t | 7.5-31.5 m | Duty A3/A4 | Constrained headroom, standard span |
| Подвесной кран | 1–10 t | 3-16 m | 3-22.5 m | Very low headroom, small-to-medium span |
| Мостовой кран с потолочным креплением | 1–20 t | 3-20 m | 3-12 m | No runway beam, suspended from structure |
| Сталепрокатный кран | 5–500 t | 7.5-31.5 m | 6–30 m | High-duty metallurgical environments |
Quick selection rule: For loads above 20 tons or spans above 31.5 m, the double-girder configuration is the only viable standard path — single-girder bridges at extreme span/load combinations produce deflection that exceeds acceptable limits under FEM 1.001 and ISO 4301. Below 20 tons, the choice between single and double girder is primarily driven by lifting height requirements: double-girder designs position the hoist on top of the girders rather than hanging below them, which typically recovers 300–600 mm of hook approach height at the cost of adding girder depth (and thus consuming more headroom above the bridge).
Получить цитатуCommon Mistakes That Make Overhead Crane Span and Lifting Height Go Wrong
Measuring Building Width Instead of Column-Center Spacing
This is the most frequent early-stage error: a facility manager measures the inside clear width of the building (wall face to wall face) and submits it as the available span. The actual usable span for a top-running crane can be 800–1,500 mm less, depending on column section dimensions and runway bracket geometry. Always measure and specify column-center spacing and confirm runway-beam and bracket details before finalizing span.
Ignoring Rail Height in Headroom Calculations
Runway rail adds height below the runway beam. QU70 rail is approximately 70 mm tall; QU100 is 100 mm. This is consistently omitted in preliminary sketches, then shows up as a 70–100 mm shortfall on installation day — a shortfall that may not be recoverable without lowering the beam or grinding down the rail, neither of which is cheap.
Specifying Lifting Height Without Accounting for Spreader Bars or Fixtures
If your load is lifted via a C-hook, magnet, grab bucket, or spreader beam rather than a direct hook attachment, the effective bottom of the load is lower than the load itself, and the effective top of the lifting assembly is higher. Both directions reduce usable working height.
Using “Standard” Span Increments Without Checking Building Grid
Overhead cranes are available in standard span increments (often in 1.5 m steps: 7.5, 9, 10.5, 12, 13.5 m…). A building whose column grid produces an available rail spacing of 11.3 m should be specified for a 10.5 m span crane (not an 11.3 m custom span), unless the process genuinely requires coverage of the full 11.3 m — in which case the column position or runway bracket needs to be adjusted to produce a clean standard span. Custom non-standard spans are possible but add lead time and cost.
Заключение
Getting overhead crane span and lifting height right before layout is finalized is cheaper by an order of magnitude than correcting either after steel is erected. The span calculation begins with column-center spacing, not building width, and deducts end-beam protrusion and safety clearance — typically arriving 1.0–1.5 m below the building’s nominal bay width. The lifting height calculation begins with your process requirement, adds hoist body height, hook approach, and safety clearance — a stack that typically totals 1.5–2.0 m — and checks the result against available building headroom.
Three actionable steps before you specify:
- Measure column-center spacing (not clear wall-to-wall) and confirm runway bracket offset with your structural engineer.
- Run the headroom formula with the actual hoist model dimensions — not an assumed 2,000 mm allowance — especially if your building headroom is under 8 m.
- If headroom is tight, specify the crane type first (Low Headroom, Underslung, or European HD), then work backward to confirm achievable lifting height before committing to the building structure.
Have questions about overhead crane span and lifting height for your specific layout? Contact Voitto’s engineering team with your building dimensions and we’ll work through the numbers with you.
Алан
Специалист по крановым решениям · Voitto Crane
Специализируемся на экспортных решениях в области мостовых кранов, козловых кранов, поворотных кранов, портовых кранов и мостовых кранов. Более 10 лет помогаем глобальным клиентам в проведении предпродажных консультаций, выборе грузоподъемности и разработке конфигураций с учетом специфики объекта.
ЧАСТО ЗАДАВАЕМЫЕ ВОПРОСЫ
Q1: What is the difference between crane span and building span when specifying overhead crane span and lifting height?
Crane span and building span are not the same number. Building span is the center-to-center distance between structural columns; crane span is always smaller — typically 1.0–1.5 m less — because runway beams, brackets, and mandatory end-beam safety clearances (minimum 100 mm per side) consume space on each side. Submitting building span as crane span is the most common early-stage specification error, and it results in a crane that physically cannot be installed.
Q2: How much headroom does an overhead crane consume above the required lifting height?
A standard wire rope hoist overhead crane typically consumes 1,500–2,000 mm of headroom above the required lifting height, accounting for hoist body height, hook approach (deadweight travel), and the minimum 200 mm top safety clearance. Exact figures depend on hoist model and capacity — confirm h₁ and h₂ from the hoist technical drawing before finalizing building height or ordering.
Q3: Can I increase lifting height without raising the roof?
Yes, within limits. A low-headroom hoist can recover 200–400 mm compared to a standard hoist of the same capacity. An underslung (underhung) crane eliminates runway rail height entirely, recovering a further 70–100 mm plus the full runway beam depth. If these gains are still insufficient for your process requirement, the building headroom is the binding constraint and a structural solution is required.
Q4: What span range suits a single-girder vs. a double-girder overhead crane?
Single-girder cranes are practical up to roughly 31.5 m span and 32-ton capacity in standard configurations; beyond those envelopes, girder deflection under load becomes the governing design constraint and a double-girder bridge is required. Double-girder cranes extend span coverage to 50 m and capacity to 800 tons in standard ranges. For the same span and load, the double-girder design also provides higher lifting height, because the hoist sits on top of the girders rather than hanging below them.
Q5: How do I specify lifting height for a crane using a grab bucket or spreader beam?
Add the closed height of the grab bucket (or the drop length of the spreader beam below the hook) to your required working lifting height, and add the height of the lifting attachment above the hook to the hoist assembly dimension stack. Both ends of the system grow simultaneously, so the effective headroom consumption is greater than for a bare hook lift. Always include full rigging and attachment geometry in the overhead crane span and lifting height calculation — not just the load height.